Thanks for a good deed!
Thanks to Jeremy Clark on Bellini at Wicor North - who saved a workparty at Wicor North with the last of his petrol supply from his generator to get our workboat (Maurice Gates) home. More »
7 Nov 2025
Today is the very last day for moving your boat from Weevil Lake!
Pontoon removal starts tomorrow, Sunday 26th. More »
19 Oct 2025
Pontoon Preparation is complete, well ahead of schedule, so ...
... the planned pontoon working parties for the next 2 weeks are cancelled. Thank you everyone for your efforts. More »
3 Oct 2025
There is now no lighting on the pontoons ....
... so please take extra care these dark evenings, and wear a flotation device More »
30 Sep 2025
Upcoming events
| Nov 8 |
09:00 - Management Committee Meeting,…Meeting start time 10am. The clubroom is required from 08.30 |
| Nov 8 |
10:00 - Electric Card ShopIF YOU REQUIRE CREDIT TOP UP |
| November 24-25 |
Work parties » New Water Pipes in Pontoon G/H…new water pipes |
| Nov 24 … Dec 21 |
Work parties » New Electric Cables to Pontoon…New Electric Cables |
| Nov 24 … Dec 21 |
Work parties » Replace Electric BollardsBollards |
| Nov 24 … Dec 21 |
Work parties » The Pontoon replacement works…stores |
| Nov 24 |
Work parties » Concrete to electrical duct in…excavate shingle. Concrete Manhole/ duct to fix in place |
| Nov 25 … Dec 21 |
Work parties » Pontoon Facilities Replacement…work party to replace facilities on pontoons. |
| Nov 26 |
Work parties » Replace life buoys to G/H. |
| Nov 26 |
Work parties » Fit Pontoon Ladders - G/H. |
| November 28-29 |
Work parties » New water pipes to E/Freplace pipes and hose reels |
| Nov 30 |
Work parties » replace Life buoys to E/F & J. |